1. The material rack and the material trough should be installed straight, and should be aligned with the guide cylinder, and the center of the straight cylinder and the undercut hole should be aligned.

2. Rotate the flywheel by hand, check the transmission mechanism and working device, adjust the clearance, tighten the bolts, start the idling operation, and confirm that the operation is normal.


3. According to the diameter of the straightening steel bar, select the appropriate straightening block and transmission speed. The diameter of the straightening block should be 2-5mm larger than the diameter of the steel bar.


4. The straightening block is not fixed, and the material cannot be fed until the protective cover is covered. It is strictly forbidden to open the protective cover of each part and adjust the gap during operation.


5. When the steel bar is fed in, the hand and the traction sheave should keep a certain distance and not approach.